loading
December 20, 2021
Digging Begins

Digging began on December 20th!  A truly horrible time to begin construction on a house, but we had no choice.

December 22, 2021

January 5, 2022

January 5, 2022
Construction Road

To preserve our main road, we began building our construction road.

January 5, 2022
Swimming Pool

Work began on the pool

I wanted the pool to be a lap pool since I swim laps for exercise.  And I wanted it positioned lengthwise along the lake so that one could stand in the pool and lean over the edge to watch a wakeboarder get towed behind the wave runner as I envisioned.  The concrete structure of the pool needed to be constructed before the house because it would been very difficult for the concrete trucks to get around the east side of the house after the house was built.

Above is the artist rendering of the pool

January 5, 2022
Construction road completed

January 10, 2022
Pool Construction

January 13, 2022
Pool Construction

Tarp to allow pool guys to keep working in cold weather.

March 2, 2022
Footings

Preparing for house footings by Rick Vernier who, because of Barry Hayden, gave me a special price.

Footings being poured

Pool construction coming along on March 3, 2022

March 15, 2022
Footings

Very, very difficult footing job

March 17, 2022
Concrete Forms

Formed boarded concrete forms, which I wanted because of seeing the look at Tahoe, being set.

More Pool Work being done.

March 29, 2022
Concrete Forms

April 1, 2022
Walls Poured
Walls begin being poured Massive wall thickness!
April 19, 2022
Concrete Walls

May 12, 2022
Concrete Walls
Again, super thick walls
May 20, 2022
Concrete Walls

June 20, 2022
Flyover

July 13, 2022
Concrete Walls

July 13, 2022
Pool Vault
Desiring a pristine look on the peninsula, I chose to hide the pool equipment in a vault.
August 23, 2022
Pool Vault

Pool vault complete!

September 5, 2022
St. Louis Homes
Dave Schaub provided us with an artist’s rendering for his advertisement in St. Louis Homes.
September 14, 2022
View From Above
A Skywagon’s perspective of the work done around Lake C&H And hedge row removal on northeast side of Lake Lori Ann I can’t tell you how hard it is to be both pilot and photographer!
September 14, 2022
Retaining Wall

Mike Yount’s retaining walls start on September 14, 2022

September 21, 2022
Retaining Wall

October 2, 2022
Wedding Day!

Stef and I got married on October 2, 2022.  Words can’t express how much Stef has contributed!  I introduced her to Amy McCoy, our interior designer, in April 2022, and, since that time, Stef has provided countless ideas and caught many areas which needed attention.

October 29, 2022
Another Fly Over

November 1, 2022
Building Materials
Massive beams delivered.  Barry told me that very big houses have 35 lb/ft beams.  This particular beam is a 150 lb/ft beam.
November 3, 2022
Dirt Work

Dirt needed to build up the house area taken from just north of the house.

November 3, 2022
Geothermal Loop

Geothermal loop being laid in lake.

November 7, 2022
Fire Pit

Dave Frost’s fire pit construction starts on November 7, 2022. Again, I felt this fire pit needed to be completed before more of the house construction since big trucks needed to get by the house to deliver large stone.

November 10, 2022
Fire Pit

November 14, 2022
Steel Erection Begins

Steel erection begins on November 14, 2022 by Steel Workers Union which identified this project as a commercial job due to the size and complexity of the steel structures.

November 17, 2022
Trusses Delivered

Very expensive Red Built trusses delivered on 11/17/22.  We chose Red Builts because the lower level ceiling was going to be an industrial exposed look.  Also see large laminated beams which were all designed by Debbie, a structural engineer.

A very heavy duty web!!!

Stef thought a swing on this tree would be great so a swing she got.

November 23, 2022
Check in from above

November 23, 2022
Framing Begins

Rick Range (pictured here…we love Rick!!!) and his Mittendorf team, another commercial construction company, began framing the house on November 23, 2022. Rick said that this was one of the most challenging projects he has ever done. Even though the drawings were in great shape, the drawings don’t instruct how to frame the house and this one, according to Rick, was very, very difficult.

November 29, 2022
Fire Pit
Fire pit taking shape.
December 2, 2022
Retaining Wall

We worked out a tricky area to locate this retaining wall

December 6, 2022
Fire Pit Complete

Completed with lights, electrical outlets, water, sump pump, and speakers.

 

December 28, 2022
"The Wing"
“The Wing” erected on December 28, 2022 A job that I wouldn’t sign up for Stef supervising from her new perch!
January 26, 2023
Walls going up!

Stef balancing her way into the house which began to be stick built

January 29, 2023
Taking Shape

Final shape starting to take shape on January 29, 2023.

February 21, 2023
Progress!

March 14, 2023

April 10, 2023

May 6, 2023
Hydronic Radiant Floor

Hydronic radiant floor heating being laid.

May 10, 2023
Lower Level

A look at the lower level.

May 15, 2023
Garage
Garage flatwork on May 15, 2023 Now on the 6th month of framing here on May 15th.
May 18, 2023
New Ride

Our new Can-Am Commander

May 31, 2023
Roofing Started
I must have gotten a little low with this shot from the Skywagon!
June 21, 2023
Setting Windows

Starting to set windows.

July 6, 2023
Hydronic Radiant Floor
Hydronic radiant floor heat throughout the lower level
July 14, 2023
Lower level flatwork

July 21, 2023
Plumbing
Plumbing starts on July 21, 2023
July 31, 2023
Pool

Dave Hunt matched the pool boarded concrete to the house

August 4, 2023
More Framing

Terbrock contractor begins lower level framing. For the past four months and for the next six months, our contractor only devotes one to two carpenters on our job drawing our job well past its due date of March 31, 2024.

August 16, 2023
Windows

Because of a lack of carpenters, it takes Terbrock seven months to set all of our windows.

August 19, 2023
Progress
Stef working with L to R Greg Terbrock (Owner of Terbrock Luxury Homes), Amy McCoy (outstanding interior designer, Owner of McCoy Design Studio), Norm Robinson (outstand Brighton electrician project leader), and Gary Jokerst (outstanding Terbrock project leader)
September 14, 2023
Pool Concrete

Pool concrete flatwork

September 22, 2023
HVAC

Sigman’s HVAC ductwork starts

September 27, 2023
Boilers

Boilers and boiler storage tank for hydronic radiated floor heat.  Sigman does nice ‘n neat work!

September 28, 2023

Front house windows still being set

October 3, 2023
Progress
One of three HVAC units An example of one of Stef’s many contributions. She sought to add a window here so that a person entering front door could see elevator cab rise or lower PLUS add cab visibility from inside cab
October 4, 2023
10/4
10/4, good buddy.  10/04/23 that is. Dave Frost and his landscaping team do a great job too! Thank you, Harold Hughes. You are an amazing friend!!! Thanks again, Harold! Barry purchases and adds a vintage 1880 wagon to his property. Barry and Debbie Hayden have treated us like gold. Barry has been incredibly helpful in providing construction advise and vendors to our project.
October 6, 2023
Beautiful Progress

October 9, 2023
Lake Dock
Roger Keim building our dock. Of course, he did a GREAT job. Roger that!
October 15, 2023
Stairway added

Stairway being added on October 15th.

October 17, 2023
Progress

Cedar siding sealed

Lower level framing, started on August 4, 2023, still not completed on October 17, 2023

October 21, 2023

Starting to enjoy Miles’s Meadow.

November 3, 2023
Patio
Able to squeeze in patio flatwork before winter sets in. Stef wrote 18 Bible verses on the studs. Our five kids each contributed their own favorite verse too.
November 7, 2023
Land Work

Burning south dam vegetation growth.

November 9, 2023
Fireplaces

Lower level fireplaces delivered and installed by C Bennett.

November 11, 2023
Fireplace

See-thru fireplace from main living room through to our master bedroom now added.

November 21, 2023
Brrrrrrr

Stef all bundled up in the Muffic (Music Room + Office).

It’s November 21, 2023 and Terbrock still hasn’t gotten our house closed up. They are still putting in exterior doors and windows after beginning this project in May.

November 28, 2023
Flyover

Yeah, I might have flown a little low here to in my buggy.

November 29, 2023
More Progress
Burying a 1000 gallon propane tank. Still adding cedar soffit, patio ceiling, and siding After several days of preparing the soil, this picture shows Dave Frost himself sitting on the back of his truck adding midwest wildflower seed on our fields to convert them to a “Milesish” meadow.
December 5, 2023
More Progress

The house is finally closed up with garage doors for winter.

Spiral HVAC tube being added

Composite decking just added

December 8, 2023
Electric Connection

Electric connection to the house completed.

December 13, 2023
Concrete Poured
More concrete pads being added. Black Mexican pebbles will go in the spaces Kevin Charles Voges + Stephenie Miles Voges
December 21, 2023
Amp Service
800 amp service Electrical service inside the house which includes auto switches for generator
January 11, 2024
Utilities
Two of the four hot water heaters. The other two HVAC units and the other two hot water heaters Electrical service at the D-mark and a look at the valving for the garage hydronic radiated floors LED lights being installed by Brighton
January 18, 2024
New Room

In July 2023 Alexis moved out of her dad’s house and chose to live with Stef and me so we changed our golf simulator room to Alexis’s bedroom. To do that, we had to replace her exterior window with an egress window and build a wall to give her privacy. Doing so would have eliminated that west view of the lake so we took the old exterior window and added that to the wall so we once again had a view of the western side of the lake.

January 23, 2024
Front Door

Front door added

January 26, 2024
Insulation
Insulation started on January 26th. This is a super insulated house. The insulation company said only about 10% of the houses they do are as insulated as ours. I need this level of insulation to reach the goal of an energy independent house. In a few years we plan to hide solar collectors on the east side of the house. A LOT of spray foam insulation!
February 1, 2024
New Sign

Because of who Stef is, I wanted to name this whole farm after her. At dinner with Kim and Rob, Kim suggested the name “Miles Meadow”. That’s it!!! Dale Sign made this sign, but Harold helped me plant the sign in God’s earth. Stef’s middle name is Miles. After Kim made the suggestion, I immediately researched and developed plans to convert our fields to a meadow.

February 6, 2024
Siding

Cedar siding

February 9, 2024
Insulation
Wall insulation And then batt insulation over the spray foam insulation.
February 24, 2024
Drywall
In one day on a Saturday, 29 men drywalled the entire house! No kidding!!! Alexis and Stef during the very busy drywall day
February 26, 2024
Drywall
Looks so much more done when the house gets drywalled, doesn’t it. Dave adding composite decking to the yoga deck. Dave always such a great job!
February 28, 2024
Drywall Taping
Now for the taping which took two weeks When I was working on the design with our architect, I got great help from Jay Prigge (on the right). The whole inspiration for this house came from seeing these types of houses (during snowboard trips) which Jay built in Tahoe. When looking at about 400 Martis Camp houses for the purpose of finding an inspiration house design to work from to look good on our peninsula, Jay and I both arrived at the same house INDEPENDENTLY!!!
March 8, 2024
TIMEOUT!
Stef getting sent to a TIMEOUT! Gary and Stef going over details in the Master Bathroom
March 8, 2024
Bathroom Design
Stef signaling that she is going to take a left hand turn.  Naw, actually she is thinking about another way to mount mirrors.  During design phase, I requested to move the shower and toilet area to the west wall so we could open up the east side for a beautiful view.  Now that the sinks are on the east wall, what are we going to use for mirrors?  Our interior designer resolved this with forthcoming suspended mirrors.  Working with the Stef/Amy interior design team is fun! The drawing on the left shows that long I-beam on the left getting drywalled. When I saw that this was going to be drywalled over, I asked for some modifications to the wood inside the I-beam and change out bolts so that the beam would remain visible.
March 19, 2024
Tiling Begins

Tile beings on March 19th.

March 26, 2024
More Progress

This guest shower design is the result of Amy McCoy’s creativity and, believe me, the tile guys did appreciate it one iota!

April 14, 2024
More Tiling
Guest bathroom tile Master Bedroom tile against transparent fireplace wall This tile going from master bedroom to bathroom in hallway and bathroom is probably my favorite tile in the house Cabinets starting to arrive…these in the lower level workout room
April 16, 2024
New Lights
Living room light hung April 16th. Stef picked this 300lb light piece out…’will look great with in this room! Now that we have electric to the firepit at the end of the peninsula, for four hours I cleaned it out to get ready for the summer/fall ‘24
April 18, 2024
Progress
Muffice shelving going up. Because we process for Kohler generators at TMW, we installed a Kohler generator for the house.
April 21, 2024
New Neighbors

Guess who moved in as neighbors on the other side of the road?  The Bax’s and their beautiful Friesian horse named Finley.  They added an $80,000 fence, plan to purchase a Clydesdale, build a barn, and board another horse.  Stef asked if they could board a horse for her and they agreed.  Wow!  Stef is in heaven!  Gavin will probably work at their barn to take care of their horses.

April 24, 2024
Progress
Doors arrived Pantry shelves being installed We didn’t want anything to block our view from our master bedroom and that includes a TV so this 350lb contraption was added to our ceiling on April 25th as a flip-down TV.
May 1, 2024
Progress
Doors being installed Guest shower completed. Look at that intricate tile job! Whew! Elevator installed. We chose a full glass elevator so we could see the mechanics of the elevator from inside or outside the cab.
May 3, 2024
Progress

Found a water moccasin in our pool

Elevator mechanical room with hydraulic power unit

Andrew working on getting the elevator operational

Lower level walk-up bar cabinets being installed

May 5, 2024
Elevator

Our elevator works!

May 8, 2024
Flooring

When the walnut hardwood floors began getting installed on 05/08/24, we were alarmed because they looked very different than the sample.  We called my very good friend, Steve Lauer, who supplied the flooring and he said not to worry…uhm, he said not to worry about 10 times!

May 15, 2024
Progress
Building the road up on the east side up to the house. Dave Frost’s guys piping water from gutters all the way to the lake.
May 17, 2024
Progress
In order to keep the Canadian geese off our peninsula, I added a coyote. Immediately thereafter, the geese left the peninsula and all gathered out in the water to take a look. Kitchen cabinets being installed
May 29, 2024
Progress
Master toilet and cabinet installed I noticed paint flaking off the exterior steel beams so I requested that all exterior beams be stripped down and re-painted.
May 31, 2024
Progress
Dave does such a good job installing cabinetry. Here’s a look at the master bathroom sink cabinet. Dekko added to the workout room to give the lower level an industrial look which I felt was especially important for the workout room. Greg’s guys did a great job adding Dekko to the lower level fireplace area.
June 2, 2024
Progress
Gene Meurer’s desk coming along nicely. Notice that the angle of the desk on the left matches the angle of the muffice south windows. Gene is also working on the subwoofer box as a piece of organic material that will hide the subwoofer in the 1st floor living room.
June 7, 2024
Progress

Outside grille cabinets installed


Back step treads installed and stairway painted

Lower patio remote control blinds installed so that we still be outside even during buggy nights.


The pool finally got plastered. Love the super light blue color because I know it will look great with water. I have never liked the dark blue pools surfaces.


Muffice carpet

June 9, 2024
Flooring

Steve said that he found some small circular scratches in the polisher so he himself sanded the entire floor back down. And then finished up the floor…wait for it!!!

Here’s why he said not to worry. I told Steve that he didn’t at all provide us the flooring he said he would…the flogging we got was MUCH better!

Another picture

June 15, 2024
Pool Time
Although the pool wasn’t completed, Stef and I got to enjoy the first night of our pool. I should have said, Stef, a snapping turtle, and me. Stef found out after I swimmed right over it. I then picked it up with the pool cleaner net and threw it in the lake. Whew, that was a close call!
June 19, 2024
Water Softener

Water softener installed
on June 19th.

June 20, 2024
Progress

Kitchen Island


Cable being added to stairway

Master closet almost completed


Gary loves to look at himself. No, actually he and I are working on a height for the suspended master bathroom mirrors

June 21, 2024
Enjoying Outside

Firepit lights work


Enjoying a quiet night at the pool

June 24, 2024
Countertops

Countertops arrive

June 27, 2024
Reading Seat

Reading seat arrived

June 28, 2024
More Tiling

Mike with SFI adding Italian tile to the laundry room

June 29, 2024
Progress

Asphalting auto court and rest of road in one day!


Adding boat launch

“Snapped a picture” with the swans in the foreground on asphalt day

Many times the “executed” turns out to be better than the plan

July 1, 2024
Progress
St. Louis Closets added closet shelving all over the house St. Louis Closets also installed the cabinets as well
July 3, 2024
Progress
Because we needed a wall area to support the upcoming glass elevator interlock doors, Dave began framing these on the 1st floor and lower level The Muffice (Music Room / Office) cabinets are almost done
July 10, 2024
Progress

Cladding FINALLY starts so Expert Metal Fabricators started hanging the “7.2” panels first


Another pic of the start of the cladding…really looking forward to the smooth panels

July 11, 2024
Steinway

Moving our 1463 lb concert grand Steinway into the Muffice


What a relief to have this instrument home, a piano built in 1885.

Grabbed Dave to help the C Bennett guys lift this 430 lb outdoor fire pit to its home on the 1st floor patio

July 12, 2024
Progress
Faucets installed throughout the house by Engineered Plumbing…also see marble backsplash added by SFI We found some swirls in the master closet floor so Steve Lauer handscraped the floor bare and resanded and stained the walnut floor once again…amazing service!
July 15, 2024
Progress
Lower level concrete polishing FINALLY begins…yay! Stef and I put the pool box together and we received the table/chairs and chaise lounges the next day.  
July 19, 2024
Progress

SFI completed the lower level concrete floor polishing which looked horrible…see picture below.

We had no choice but to unload this beautiful early 50’s professional Brunswick pool table that was refurbished by a guy in Manhattan, KS.  Interestingly enough, that pool table originally came from Kansas State University student center.

Our live edge table arrived.  The trucker first dropped off a boxed electric car battery.  Fortunately, we could tell that there couldn’t be a table inside so we were able to stop the trucker in time for him to drop off the correct delivery.

Stef had this table made in Canada.  We wanted the big steel base and then a live edge top to soften the tone in the house.

July 23, 2024
Moving Day!

It’s Stef’s dad’s and my dad’s birthday…and it’s also moving day!  We had no choice but to move into our new house even though the house needs about another 1-½ months of work to complete the house.

July 28, 2024
Ugh!

The same company that did a horrible job on the lower level concrete polished floors is the same company that now messed up our garage epoxy floor.  The below picture of the floor discoloration is the least of the problems.  We now need to wait for another company to grind down both floors and then start over polishing the lower level concrete floor and re-epoxing the garage floor.  UGGGHHH!

July 30, 2024
Progress

Our patented steel process, EPS (Eco Pickled Surface, www.epsprocess.com) is now going up on the fireplace wall.

July 31, 2024
Progress

With many EPS cells processing for many applications globally, this has got to be a new application for EPS.



August 1, 2024
Progress

Alan Mueth spent many careful hours getting a Superior coil (our biggest TMW customer) EPS’d, stretcher leveler CTL’d, and then plasma cut at Red Bud Industries.  Including preparing the wall, these panels took four guys an entire week to glue these panels to the wall.

August 16, 2024
Progress

Here on Clayton’s birthday, ACM panels begin going up!  These ACM panels will take a full month to install.

And Jay Prigge’s art is also hung.  We had this art hanging at our Tundra house, but the location didn’t do that art justice.  This is the perfect home for this monstrosity!

August 19, 2024
Progress

Garage Forceoff all of SFI’s epoxy and re-applied doing a great job!

Workshop area for my dad’s machinery.  Stay tuned for the machines’ arrival on 08/30/24

Very deep bays, electric car hookups, transparent see-thru garage doors, and Big A$$ Fans

Stef and I organized the totes and other stuff in our new garage shelves which St. Louis Closets provided and installed.

 

August 20, 2024
Progress

It’s time for the construction road to go.  A big milestone for our project.

September 9, 2024
Progress

Heintz getting started on the pool vault cover

September 10, 2024
Fireplace Surround

On 08/22/24 when we received this fireplace surround, I saw how it was built so chincy.  ‘Found out that it was built from a workers’ drawing and not included in the construction drawings.  It needed to be beefier!

Eric Guebert did a super great job on making the fireplace surround more robust.  He basically adding steel on the back side of the C-channel to make it twice as thick.

September 12, 2024
Fireplace Surround

Now that the surround has been added, we could see that we needed to get the EPS painted because the EPS doesn’t contrast well with the hearth.

September 15, 2024
Flyover

I sold the Skywagon in August and bought an F33A Beechcraft in September.  This is the first picture of the house from the “Beech” after quite a bit of landscaping and grass planted by Dave Frost’s team.  Pictures are a little harder to get from the low wing Beech.

September 16, 2024
Progress

After three weeks of work, Custom Crete did a great job regrinding SFI’s lower level concrete polishing job off and providing a beautiful polished floor!

Now that the floor was well polished, we moved appliances into the lower level bar.  The background on the bar gives it a bit of an aviation look.

September 22, 2024
Progress

These bar stools that Stef chose also adds to the aviation vibe.

September 22, 2024
Progress

Sue Greene painting the EPS with texture.  What a great job!

September 24, 2024
Progress

Dave Frost’s guys adding plants to the three levels of front planters

September 25, 2024
Progress

Painted EPS wall completed